At our first work session in 2015 Joel and Kent started installation of the "new" 1970s CVCC alternator, per recommendations from Van's Aircraft and an EAA technical counselor Kent met in Oshkosh a few years ago. Below are three pictures of our initial work compared to a completed installation. This task requires the following:
1. drill out slightly three top holes in the alternator mounting bracket (from Van's)
2. fabricate mounting bracket for tensioner arm (supplied by Van's) from steel angle stock
3. fabricate tie brace to connect lower alternator boss to alternator boss
So far things are going according to our expectations with no major challenges.
Above - test installation of new alternator on Lycoming O-290 G/D.
Below - completed installation on similar engine.
A Stitts Skycoupe Restoration Project
The Stitts Skycoupe is also known as Stitts SA7 D
Monday, January 5, 2015
Sunday, December 28, 2014
Work Session 12/27/14
Yes, we're still at work! In fact, since moving our project to Cox Field approximately one year ago, we have made steady progress on many fronts. We meet twice weekly, Tuesday evenings and Saturday mornings. In the past year, here are some of the main things we've accomplished on our Skycoupe:
1. Fabricated all wing struts, two per wing, including secondary (strong!) bracket on fuselage.
2. Redesigned fuselage tubing to ease entry - a large diagonal tube was removed and replaced by two triangular frames. Kent (mechanical engineer & aircraft designer by profession) analyzed the before-and-after design and found the new design to be stronger. Tube cutting and welding were done by Andy and Chris.
3. Redesigned the doors to hinge upwards, basing the design on the Eurofox/Aerotrek aircaft owned by chapter member Andrey Piskarev.
4. Fabricated prototype seat bottom and seat back based on dimensions from a leading manufacturer of aircraft seat cushions for certificated aircraft.
5. Fabricated and installed left aileron and torque arm. This was a major, complex process that was led by Joel with much assistance from Andy and Chris. The results are excellent! Joel is now completing the right aileron.
6. Finished covering of stabilizers and tail control surfaces, including rib stitching and coating with Polybrush and Polycoat (silver). Work done by Kent.
7. Started adaptation of main wheel pants salvaged from a Spezio Tuholer. Work by Kent.
8. Acquired then sold Spezio Tuholer wreck, creating good revenue and some major components for the group. Led by Konrad.
9. Designed and fabricated left and right fuselage longerons, given the plane a more rounded cross-section to reduce drag. This required some modification of the door frame. Led by Andy.
10. Designed and fabricated multiple panel prototypes. The final design is now ready for fabrication from thick aluminum. Most of the instruments and related components have been acquired. Chris, an electrician from training, will lead the electrical design of the aircraft and all wiring.
11. Designed and fabricated a secondary panel in the rafters for the COM and Transponder.
There were many other things we did in the past year not mentioned here. The current major projects are:
1. Completion of the right aileron. Joel
2. Design of electrical system and panel mounting. Chris and Kent
3. Completion of fuselage longerons and battery compartment door. Andy
4. Design and fabrication of baggage compartment walls. Konrad
5. Fabrication of auxiliary fuel tank and related components. Joel
6. Elevator trim system. Andy
We are targeting the spring of 2015 for covering of the fuselage and summer of 2015 for final assembly.
Above: Secondary panel (.032 aluminum) holding COM and TX mockups.
Above: the right-hand fuselage longeron and beginnings of a battery access door frame can be seen here. Andy is lead on this work.
Below: On October 18th, 2014, the original builder of our Skycoupe, Mr. Paul Schauber Sr. of Baltimore, MD paid us a visit with his two sons. Below are images from this historic meeting of builders and an article about the original construction that appeared in the December 2010 newsletter of RAMM, the Retiree's Association of Martin Marietta Corporation where Paul spent much of his career as a technician.
Above: The Skycoupe in its new shop at Cox Field.
1. Fabricated all wing struts, two per wing, including secondary (strong!) bracket on fuselage.
2. Redesigned fuselage tubing to ease entry - a large diagonal tube was removed and replaced by two triangular frames. Kent (mechanical engineer & aircraft designer by profession) analyzed the before-and-after design and found the new design to be stronger. Tube cutting and welding were done by Andy and Chris.
3. Redesigned the doors to hinge upwards, basing the design on the Eurofox/Aerotrek aircaft owned by chapter member Andrey Piskarev.
4. Fabricated prototype seat bottom and seat back based on dimensions from a leading manufacturer of aircraft seat cushions for certificated aircraft.
5. Fabricated and installed left aileron and torque arm. This was a major, complex process that was led by Joel with much assistance from Andy and Chris. The results are excellent! Joel is now completing the right aileron.
6. Finished covering of stabilizers and tail control surfaces, including rib stitching and coating with Polybrush and Polycoat (silver). Work done by Kent.
7. Started adaptation of main wheel pants salvaged from a Spezio Tuholer. Work by Kent.
8. Acquired then sold Spezio Tuholer wreck, creating good revenue and some major components for the group. Led by Konrad.
9. Designed and fabricated left and right fuselage longerons, given the plane a more rounded cross-section to reduce drag. This required some modification of the door frame. Led by Andy.
10. Designed and fabricated multiple panel prototypes. The final design is now ready for fabrication from thick aluminum. Most of the instruments and related components have been acquired. Chris, an electrician from training, will lead the electrical design of the aircraft and all wiring.
11. Designed and fabricated a secondary panel in the rafters for the COM and Transponder.
There were many other things we did in the past year not mentioned here. The current major projects are:
1. Completion of the right aileron. Joel
2. Design of electrical system and panel mounting. Chris and Kent
3. Completion of fuselage longerons and battery compartment door. Andy
4. Design and fabrication of baggage compartment walls. Konrad
5. Fabrication of auxiliary fuel tank and related components. Joel
6. Elevator trim system. Andy
We are targeting the spring of 2015 for covering of the fuselage and summer of 2015 for final assembly.
Above: Secondary panel (.032 aluminum) holding COM and TX mockups.
Above: the right-hand fuselage longeron and beginnings of a battery access door frame can be seen here. Andy is lead on this work.
Below: On October 18th, 2014, the original builder of our Skycoupe, Mr. Paul Schauber Sr. of Baltimore, MD paid us a visit with his two sons. Below are images from this historic meeting of builders and an article about the original construction that appeared in the December 2010 newsletter of RAMM, the Retiree's Association of Martin Marietta Corporation where Paul spent much of his career as a technician.
| Paul Schauber Sr. explains details of his work to Kent |
Above: The Skycoupe in its new shop at Cox Field.
Saturday, March 2, 2013
Work Session 3/2/2013
Terry, Andy, Kent and Steve Johnson met for breakfast at Al's Diner at 0800 then worked from 0900-1300 on a variety of projects including riveting the seats, the airbox and (after Konrad came a bit later) the brakes. Terry gave Steve a good lesson in setting rivets in the seat bottoms and backs, something Steve mastered in a few minutes. Andy and Kent used the panel mockup to look into what will be needed to mount it offset from the frame to provide clearance for instruments. We found that the panel can be much shorter than originally expected, leaving more leg room than expected. We'll also not need a lower central extension to the panel. The panel mockup will now be modified and we'll look at the best means to mount it in a way that makes removal simple for assembly and maintenance.
We need someone to take 'ownership' of the completion and assembly of the ailerons. Who can help?
We need someone to take 'ownership' of the completion and assembly of the ailerons. Who can help?
| Steve Johnson shows off one of the seat pans, nicely riveted. |
| Terry and Steve set rivets on the seat back. |
Friday, February 22, 2013
Instrument panel mockup
| Skycoupe instrument panel mockup 2/22/2013 |
Yes, a few BCAC members have been making progress this winter. For instance, at Noel Falwell's suggestion, Kent created this mockup of a new instrument panel with full-scale images of instruments tentatively planned for the airplane. Following is a list of instruments being considered or already purchased:
Stits SA-7D Skycoupe Instrument List
- GPS/Moving Map - iFly 700 GPS gimbal mount + antenna
- http://ifly.adventurepilot.com/HOME.aspx
- Dimensions: 7 1/4" X 4 1/2" X 3/4"
- MGL Flight-2 Primary Flight Instrument (MGL Velocity Single)
- http://www.mglavionics.co.za/
- Dimensions: 3.346" X 3.346" X 2.047"
- MGL E1 Universal Engine Monitor
- http://www.mglavionics.co.za/
- Dimensions: 3.346" X 3.346" X 2.047"
- Radios
- Garmin Apollo Slimline SL-30 NAV/COMM
- http://www8.garmin.com/products/sl30/
- Dimensions: 1.3"H x 6.25" W x 10.5" D
- Garmin Apollo Slimline SL-40 COMM
- http://www8.garmin.com/products/sl40/
- Dimensions: 1.3"H x 6.25" W x 10.5" D
- MGL V-6 w/Intercom
- http://www.mglavionics.com/html/radios.html
- Dimensions: 2.40"H x 2.40" W x 4.2" D
- Intercom
- Flightcom 403mc (donated by Michael Crowder)
- http://www.flightcom.net/general-aviation/intercoms-ga/403mc/
- Dimensions: 2.375″ W x 1″ H x 2.625" D
- MGL V-6 COMM w/Intercom (see above)
- Transponder
- Garmin GTX-327 $1200
- http://www8.garmin.com/products/gtx327/index.html
- Dimensions: 6.25"H x 1.65" W x 8.73" D
- Fuel/Air Mixture gauge = Innovate MTX-L AFR
- http://www.innovatemotorsports.com/products/MTXL.php
- Dimensions: 2.0625"H x 2.0625" W x ~3.0" D
- Inclinometer
- http://aircraftproducts.wicksaircraft.com/item/aircraft-instruments/inclinometer/1576s?
- Dimensions: 3.5"H x 1.5" W (surface mount)
- Throttle Dia. 1.5" ?
- Mixture Dia. 1.5" ?
- Primer (?)
- Magnetic compass
- http://aircraftproducts.wicksaircraft.com/item/falcon-gauges/falcon-gauge-magnetic-compasses/mcdn-2?&plpver=10&origin=keyword&by=prod&filter=0
- Dimensions: 2.0" Dia.
- Switches Left - Contura-2, Carling
- Master On/Off
- L-Mag On/Off
- R-Mag On/Off
- Starter - momentary switch
- Switches Right - Contura-2, Carling
- Future use
- Fuse panel - Bussman
- Headset sockets right/left
- Map box
Friday, December 7, 2012
Work Session 12/6/2012
Terry, J-P, Konrad, Jim, Andy, Joel and Kent met from 4-8 at the Skunk Works and made progress on the seats and air intake. J-P was aided by others in some detail work on his RV-12.
| The Skycoupe's new hangar |
| Terry and J-P discuss work on the RV-12 |
| Jim clecos the stiffener angles on the seat back and bottom |
| Seats, reader for riveting |
| Conrad (Konrad's friend), Andy, Joel and Konrad discuss attachment of the air intake to the lower cowl |
| Andy trims the composite air intake |
| Copper tubing works well for making smooth, symmetric trim lines |
| Skycoupe in its voluminous hangar |
Sunday, October 28, 2012
Work Session 10/27/2012
Terry, Kent, Andy and Joel met at 0700 for a hearty breakfast at Al's Diner before heading down to the Skunk Works for a full morning of work. J-P joined us during the same morning. The most important accomplishment of the day was completion of the RV-7 wings and empennage preparations for their sale. A separate posting on this blog serves as a gallery for prospective buyers. We also helped Terry rearrange a few things in the shop in preparation for coming projects. Andy continued work on the Skycoupe's air inlet scoop and fairing, and it's looking great!
| Right wing - ready for sale |
| RV-expert Joel McLaughlin put many hours into the RV-7 project, here he is with the empennage |
| Andy Thomson working on the air inlet for the Skycoupe |
![]() |
| Closeup of Andy's work - very nice shape! |
| RV builders Joel and J-P set a final few rivets in the left wing of the RV-7 |
| RV builders Joel and J-P set a final few rivets in the left wing of the RV-7 |
Thursday, October 25, 2012
Work Session 10/24/2012
A major rearrangement of the shop was made in preparation for some new major projects at the Skunk Works. Otherwise, Joel and Andy crafted a foam plug for a composite fairing for the airbox inlet. Kent and newcomer Bryan Gossage began addition of eight angle stiffeners to the seats. Present were Terry, Jim, Andy, Joel, Kent and Bryan Gossage.
The next work session will be on Saturday, 10/27/2012. We'll start with breakfast at Al's Diner at 0700, work begins at 0800. Plenty to do - seats, tail feather rib stitching, aileron fabrication, etc.
The next work session will be on Saturday, 10/27/2012. We'll start with breakfast at Al's Diner at 0700, work begins at 0800. Plenty to do - seats, tail feather rib stitching, aileron fabrication, etc.
| Andy sands the inlet plug into shape using TLAR technology |
| Airbox inlet - Mark I |
| Andy test fits the plug to the lower cowl |
| Test fit of the rough airbox inlet fairing to lower cowl |
| Newcomer Bryan Gossage prepares seat angle parts for drilling |
Monday, October 22, 2012
Work Session 10/20/12
BCAC officers met after the EAA chapter meeting to discuss completion & sale of the RV-7 parts, acquisition of a storage trailer, work scheduling, future recruiting, sale of spare carburetor, general financial issues and upcoming major tasks.
Terry, Kent, Andy, Joel, Mike Maltby, Niels & Judy Nielsen and Dan Kangas stopped by the shop on a glorious Indian Summer afternoon to work on the Skycoupe.
Andy and Joel made modifications to the lower cowl and made the first test fit of the airbox. Dan assisted.
Kent cut, drilled and clecoed the attachment hinge onto the pilot seat.
Welding on the wing struts will take place this week off-line.
Sorry, no pictures, but progress is evident. As the seats and airbox are being completed, we'll start soon on rib stitching of the tail feathers, silver coat of the same, and the panel fabrication. The ailerons also need completion. Once the struts are ready, the wings will be remounted in order to work on the aileron linkages.
Terry, Kent, Andy, Joel, Mike Maltby, Niels & Judy Nielsen and Dan Kangas stopped by the shop on a glorious Indian Summer afternoon to work on the Skycoupe.
Andy and Joel made modifications to the lower cowl and made the first test fit of the airbox. Dan assisted.
Kent cut, drilled and clecoed the attachment hinge onto the pilot seat.
Welding on the wing struts will take place this week off-line.
Sorry, no pictures, but progress is evident. As the seats and airbox are being completed, we'll start soon on rib stitching of the tail feathers, silver coat of the same, and the panel fabrication. The ailerons also need completion. Once the struts are ready, the wings will be remounted in order to work on the aileron linkages.
Thursday, October 11, 2012
Work Session 10/10/2012
Attending this session were Terry, J-P, Mike, Andy, Konrad, Jim and Kent.
Steady progress was made on the following:
Steady progress was made on the following:
- RV-7 wing tank sealed, pressurized and leak testing begun. Terry and J-P.
- Airbox upper plate/filter assembly. Andy and Mike.
- Dents in cowling worked on. Konrad, Jim and J-P.
- Large mounting hinge added to back of right seat. Terry and Kent.
| Mike works on nut plates needed for the air box top cover |
| J-P and Jim prepare the RV-7 tank for leak testing. |
| RV-7 tank ready for testing - a temporary cover plate with air connection has been added. |
| MG car expert Konrad explains the art of sheet metal repair, using a set of body dollies he brought along. |
| Konrad goes to work on one nasty dent while Jim secures the cowl section |
| Andy and Mike attempt to understand the complicated instructions that came with the airbox |
| Konrad and Jim inspected the night's work. |
Saturday, September 29, 2012
Work Session 9/29/2012
Terry, Andy, Noel and Kent enjoyed breakfast at Al's Diner at 0700, a popular place on Saturday morning. Work today included further airbox assembly, stripping old paint from some fairings and the start of seat fabrication.
The next work sessions are tentatively planned for Friday, October 5th from 4-8 PM.
| Andy attached most of the cowl and nose bowl in order to determine how best to install the airbox. |
| Andy working on the airbox. |
| Upper air box cover as it mounts to lower face of the carburetor. |
| Terry measures length of hinge needed to attach set bottom to seat back. |
| First seat with hinge in place. |
Friday, September 28, 2012
Work Session 9/27/2012
A great turnout last evening allowed us to make progress on a number of fronts:
- Repaired small leak to RV-7 fuel tank caused by poorly-cured ProSeal.
- Rounded corners and debured edges on seat panels.
- Finish ironing on empennage parts.
- Positioned old panel and planned new panel.
- Positioned seat panels and planned further fabrication.
- Mounted carburetor and cowl and planned airbox.
The next session will be on Saturday, September 29th, starting with breakfast from 7-8 at Al's Diner.
Terry demonstrates finish ironing on seams.
Jim - "Mr. Methodical" - Cronin makes it right.
Chris, chief panel designer, checks out dimensions of the old panel with the new seats and Terry's RV-9 seat cushions in place.
Above: Seat panels and Terry's RV-9 seat cushions in place. The new panel will be a few inches shorter to allow more room for knees. Right: Andy rounds the corners and takes the edge off the four seat 0.070" aluminum seat panels.
J-P carefully removes old ProSeal from RV-7 tank. For reasons not understood, it did not completely cure, leading to a slight leak. After cleaning, new ProSeal will be applied and the tank again tested.
The first iteration looks quite good! PVC piping was added to mockup air inlet and location of needed opening on the lower cowl.
Below: What it's all about - Joel describes his plans for the airbox and inlet while others listen or adds their thoughts.